Structural design of Highway 75 in the section between Nahalal and Ramat Yishai

Est. Construction Cost:
110 Million ILS

Design and Construction Period:
2010-2014

Client: National Roads Company of Israel

Geographic Location: 75 road Nahalal to Ramat-Yishai

Description: Highway 75 in the section between Nahalal and Ramat Yishai – a vehicle bridge, a bridge protecting the National Water Carrier, retaining walls (bracing L walls with soil anchors), acoustical barriers, underpasses and drainage carriers were all planned within the framework of this project

Amy Metom Role in the Project: Structural design. Design of a vehicle bridge having two 60 m long spans. The bridge deck rests on elastomeric bearings and is comprised of prestressed double T-beams with supplementary castings. Precast concrete nosings of variable cross-section were assembled on the bridge façades, giving the bridge an arched appearance.

Unique Elements of the Project: a vehicle bridge having two 60 m long spans, The bridge deck rests on elastomeric bearings and is comprised of prestressed double T-beams with supplementary castings, Precast concrete nosings of variable cross-section were assembled on the façades